Private Power Pole Installation & Power Supply Relocation Terry Hills

Project case study

Terry Hills, Sydney NSW


The problem

The customers temporary power utilised for the construction of their new home was installed in the incorrect location by another contracting company. As a result, the customer received a Defect Notice from Ausgrid giving them 21 days to comply and rectify the issue otherwise have their Power disconnected.

The solution

We were engaged to help fix this problem. We were able to provide a cost-effective, fast solution by simply removing the existing pole and relocating to its new position. We cleared the defect notice with Ausgrid keeping the customer happy and preventing any delays in the construction of their new Home.

Location Terry Hills, Sydney NSW
Project type Temporary Builders Power
Service Private Pole Installation
Equipment used Crane Truck with hydraulic Auger. EWP Level 2 truck to work on the Electricity Network.
Timeframe Urgent response window
Outcome Site made safe and supply restored

Need a power pole installed, replaced or urgently assessed?

Talk to Power Poles NSW about private pole installation, defect notice rectification, emergency replacement, temporary builders poles and Level 2 electrical solutions.